<img height="1" width="1" style="display:none;" alt="" src="https://px.ads.linkedin.com/collect/?pid=1556145&amp;fmt=gif">

05 April 2019

How to respond to a payment claim under security of payment in Victoria

If you receive a payment claim under the Building and Construction Industry Security of Payment Act 2002 (Vic), you have limited time to prepare a payment schedule.  This article explains how to do it.


sopa vic alt

1. Be on the lookout for payment claims.

A payment claim made in Victoria must state that is a payment claim made under the Act. A statement along the lines of “This is a payment claim under the Building and Construction Industry Security of Payment Act 2002” should appear somewhere on the payment claim.

A payment claim is a document that:

  • is served on the person who, under the construction contract concerned, is or may be liable to make the payment; and
  • identifies construction work or related goods and services to which the progress payment relates; and
  • indicates the amount of the progress payment that the claimant claims to be due.

Since you will only have a limited amount of time to deal with the claim, you should have a system in place to ensure that any payment claim that arrives is promptly brought to the attention of someone who will be in a position to deal with it.

2. Determine when your response (payment schedule) is due

Before doing anything else, calculate when your response is due. Assuming the payment claim is valid, your payment schedule must be served within:

  • 10 business days after the payment claim has been served; or
  • the time prescribed by the contract, whichever time expires earlier.

3. Work out how and where your response will be sent

The manner of service is critical. Once you have worked out how your response must be sent, you can work out how long you actually have to consider and prepare your response to the claim.

You should not assume that service by email, Dropbox, USB key, document management system (e.g. Aconex) or website portal will be effective. (See for example the decision of Parkview Constructions for an example of service by USB key not being effective.)

Always check the terms of your contract to see what methods of service are permitted. Also check section 50 of the Act, which may give you additional options.

If you do not serve your payment schedule on or before the due date, the claimant may have the right to recover the entire amount of the payment claim, as a debt, among other options. It is therefore critical to ensure that your payment schedule is served on time.

After you have worked out when and how your response will be sent, it’s time to start considering the substance of the claim.

4. Consider whether the claim is in fact a valid payment claim under the Act

Just because a claim purports to be a payment claim under the security of payment legislation, this does not mean that it is necessarily a valid claim.

If the claim is not a valid payment claim, the claimant will not have any rights (and you will not be exposed to any liabilities) under the Act.

A claim will not be a valid payment claim under the Act unless it:

  • states that it is a payment claim under the Act;
  • is made pursuant to a construction contract covered by the Act;
  • is made in respect of a reference date, and made on or after that date; and
  • is served on the right person.

Determining whether a payment claim meets these criteria is not always a straightforward process. If in doubt, assume that it is a valid claim and that you are required to prepare a payment schedule.

Be aware that even if it is not a valid claim under the Act, it may still be a valid claim under the construction contract.

Further, some contracts will deem a payment claim to have been approved in full if a payment schedule has not been received within the agreed timeframe. See, for example, clause 37.2 of AS 4000-1997, which states:

“If the Superintendent does not issue the progress certificate within 14 days of receiving a progress claim in accordance with subclause 37.1, that progress claim shall be deemed to be the relevant progress certificate.”

5. Consider whether the full amount of the payment claim is in fact claimable under the Act

A payment claim cannot include a claim for an ‘excluded amount’. An excluded amount is:

  • an amount that is not a claimable variation;
  • compensation payable as a result of a latent condition, time related costs and changes in regulatory requirements;
  • damages for breach of contract;
  • any claim arising at law other than under the contract.

If the payment claim includes an excluded amount and it proceeds to adjudication, the adjudicator may not consider the excluded amount. Any determination that takes into consideration an excluded amount will be void to the extent that it does so. A dispute about an excluded amount may be resolved in accordance with the dispute resolution clause of the contract or by going to court.

6. Include the prescribed details

A payment schedule must clearly identify:

  • the payment claim it is responding to; and
  • the ‘scheduled amount’, being the amount you propose to pay. (If you propose to pay nothing, the scheduled amount will be nil.)

If the scheduled amount is less than the claimed amount, you must set out your reasons for withholding payment.

7. Set out all of your reasons for withholding payment

If you do not intend to pay the full amount claimed, for each item in the claim, you should set out:

  • the amount that is agreed (if any);
  • the amount that is not agreed; and
  • your reasons as to why you do not agree to pay the amount claimed, or part of the amount claimed.

Your reasons for withholding payment must be sufficient to enable the claimant to understand why you are withholding payment.

In Multiplex v Luikens, the Court said:

“a payment schedule should not… be required to be as precise and as particularised as a pleading in the Supreme Court. Nevertheless, precision and particularity must be required to a degree reasonably sufficient to apprise the parties of the real issues in the dispute.”

When preparing your reasons for withholding payment, think about:

  • the substantial issues, such as whether certain work is claimable as a variation (by reference to the original scope), or the rates and quantities applied; and
  • the technical legal issues, such as time bars in your contract, or provisions that operate as preconditions for claiming payment (such as the giving of contractual notices).

If more than one reason applies to the same item, include them both.

If you don’t include a reason for withholding payment in your payment schedule, but raise it later in response to an adjudication application made by the claimant, the adjudicator must notify the claimant of those new reasons and allow them two business days to respond. If the adjudicator does not provide the claimant with the opportunity to respond to your new reasons, any subsequent adjudication determination may be capable of being challenged due to a lack of procedural fairness argument.

8. Have the payment schedule issued by the right person

The person required to issue a payment schedule is the person upon whom the payment claim is served (i.e. the person liable to make the payment).

It’s possible for someone else to issue a payment schedule on behalf of that person, such as a superintendent or a solicitor, provided that person has been authorised to do so.

9. Serve the document properly and keep evidence of delivery

Following the principles discussed earlier, make sure the payment schedule is delivered in the right way and by the deadline.

If you are sending documents to a physical address, check the payment schedule and the contract to ensure you are sending the payment schedule to the right place. If you are dealing with a corporation, consider conducting an ASIC search to ensure the address is current.

If you have multiple addresses to choose from and you’re not sure which one to pick, it may be worth sending the payment schedule to all of them. Serving the document multiple times would be better than running the risk of not serving it properly at all.

When you arrange delivery, make sure you obtain evidence of service, such as:

  • a delivery and read receipt if sent by email (assuming email is permitted);
  • a transmission report if sent by fax; or
  • post or courier receipts.

10. Mark your diary and be ready for an application

If you think the claimant is likely to apply for adjudication, mark your diary for the date that is 10 business days after the date you deliver the payment schedule. That is the last day the claimant will have to make an application.

If an adjudication application is made, you will only have 5 business days to prepare your response. Consequently, if it looks likely that you will receive an adjudication response, you should consider seeking legal advice at the earliest opportunity to ensure you have enough time to compile your best possible defence to the claim.

Better contracting checklist

Related Posts

About Turtons

Turtons is a commercial law firm in Sydney with specialist expertise in the construction and technology sectors.

We specialise in helping businesses:

  • improve their everyday contracting processes,
  • negotiate large commercial contracts and other deals that fall outside of "business as usual", and
  • undertake strategic initiatives, such as raising capital, buying businesses, implementing employee share schemes, designing and implementing exit strategies and selling businesses.
Morgan McIntosh | Senior Associate

Contact

Morgan McIntosh | Senior Associate

morgan.mcintosh@turtons.com

Turtons Linkedin logo

Morgan is a specialist construction lawyer in Sydney who helps companies navigate through large or unusual projects and streamline their contracting processes through simplified contracts.


morgan.mcintosh@turtons.com | (02) 9229 2901

Resources
Careers